Table 3 Data of the original schedule
Cast Heat Steelmaking Refining Casting
stij ptij Machine stij ptij Machine stij ptij Machine
1 1 0 50 Converter-1 50 45 Finery-1 95 35 Caster-1
2 30 50 Converter-2 80 45 Finery-2 130 35 Caster-1
3 50 50 Converter-1 100 45 Finery-1 165 35 Caster-1
4 75 50 Converter-3 145 45 Finery-1 200 35 Caster-1
5 125 50 Converter-3 190 45 Finery-1 235 35 Caster-1
6 175 50 Converter-3 225 45 Finery-3 270 35 Caster-1
2 7 30 45 Converter-3 100 40 Finery-3 140 35 Caster-2
8 80 45 Converter-2 125 40 Finery-2 175 35 Caster-2
9 115 45 Converter-1 165 40 Finery-2 210 35 Caster-2
10 160 45 Converter-2 205 40 Finery-2 245 35 Caster-2
11 215 35 Converter-2 250 30 Finery-2 280 40 Caster-2
12 255 35 Converter-1 190 30 Finery-1 320 40 Caster-2
3 13 125 35 Converter-2 160 30 Finery-3 190 40 Caster-3
14 160 35 Converter-1 195 30 Finery-3 230 40 Caster-3
15 205 35 Converter-1 240 30 Finery-1 270 40 Caster-3
16 225 45 Converter-3 270 40 Finery-3 310 30 Caster-3
17 255 45 Converter-2 300 40 Finery-2 340 30 Caster-3
18 285 45 Converter-3 330 40 Finery-3 370 30 Caster-3